So not much has been written on this as Rihoys have mnostly been concentrating on the roof and we've been concentrating on an influx of visitors.
The rafters are finished and all the velux apertures have been cut.
The staircase is in and most of the studwork which defines the rooms is finished.
Our issues to date are that the eaves cupboards need to be built to spec, the plumber needs to pull his finger out and we need to sort out a way to finish the exterior part between the upper and lower sections of the gable. Oh and the build is now four weeks behind, but progress has picked up.
We went to a site meeting today and all the discussions have been about detials - in stark contrast to the meetings a couple of months ago which were to discuss much larger structural issues.
All in all it's looking very exciting and we're enjoying the fact that the finishes have been chosen and the building is really shaping up so that we can see the size and visualise the spaces at last.